  • Requirements

  • req-5
    2x 20mm ring
  • req-4
    8mm righting line
  • req-4
    5mm Shock Cord

Steps

  • 1. Attach the shockcord with a bowline to the starboard aft trampoline lashing under the trampoline.
    2. Feed the other end of the shockcord through the 20mm ring in the middle of the trampoline.
    3. Feed the line through the ring in the aft middle of the trampoline.
    4. Attach the other ring to the end of the shock cord using a bowline knot.
    5. Make an eight knot at the end of the righting line.
    6. Feed the other end through the ring under the front cross beam.
    7. Then through the ring attached to the shock cord.
    8. Back to the front cross beam, through the eyelet.
    9. Make an eight knot at the end of the righting line.