Cunningham 1:16
-
Estimated reading time: < 1 min
-
Requirements
Steps
-
1. Use the 1:16 Cunningham kit and knot the d12 5mm line to the 16 mm double blocks. In yellow below.
-
2. Install the spinlock cleats on the mast using their clevis pins and the pre-installed holders.
-
3. Take the loose end of the shockcord and feed it through the 16mm block on starboard side. Attach the 16mm block on the end of the shockcord with a bowline.
-
3. Loop the cunningham line through the blocks as shown in the drawing. Red and green represent the port and starboard sides of the same continuous line.
-
For the Continuous Cunningham system keep the port side rope end length to 0.5m and the starboard side rope end length to 4m+. You can use the long end to thread the continuous system when rigging. For more information see Cunningham Continuous System in the Rigging chapter.